198   Erection and occupation of buildings and subdivision of land
(1)  In this clause, a relevant provision means section 81A, section 109M or any other provision of the Act relating to the issue of subdivision certificates.
(2)  For the purposes of section 115ZF (5) of the Act, a relevant provision applies to approved State significant infrastructure in the same way as it applies to development subject to a development consent, subject to any necessary modifications. For that purpose, a reference in section 81A or Part 4A of the Act to a development consent is taken to include a reference to an approval of State significant infrastructure under Part 5.1 of the Act.
(3)  However, a relevant provision:
(a)  does not apply unless that provision would have applied if the development was not State significant infrastructure, and
(b)  applies to critical State significant infrastructure only if the Minister, when giving approval to the infrastructure under Part 5.1 of the Act, makes it a condition of that approval that the provision applies.