Contents (2000 - 557)
Skip to content
Environmental Planning and Assessment Regulation 2000
Historical version for 30 September 2015 to 1 October 2015 (accessed 8 April 2020 at 20:08) Current version
Part 16C Division 1
Division 1 Preliminary
268Y   Interpretation
(1)  In this Part:
consent ballot—see clause 268ZC.
co-owner of a lot means a person who owns a lot jointly with 1 or more other persons.
(2)  Words and expressions used in this Part have the same meaning as they have in Schedule 5 to the Act.
268YA   Subdivision works
(1)  For the purposes of the definition of subdivision works in Schedule 5 to the Act, works for the following purposes are prescribed:
(a)  gas supply,
(b)  remediation of contaminated land,
(c)  demolition of a building or work if the demolition is required to carry out other subdivision works.
(2)  In this clause:
contaminated land has the same meaning as in Part 7A of the Act.