136N   Principal certifying authority to be satisfied that preconditions met before commencement of work
(1)  This clause applies to building work or subdivision work that is the subject of a complying development certificate.
(2)  A principal certifying authority for building work or subdivision work to be carried out on a site, and over which the principal certifying authority has control, is required to be satisfied that any preconditions in relation to the work and required to be met before the work commences have been met before the work commences.