Environmental Planning and Assessment Regulation 2000
Historical version for 1 March 2010 to 25 March 2010 (accessed 5 August 2020 at 15:56) Current version
Part 6 Division 12 Clause 120
120   Notification of concurrence authorities and approval bodies
(1)  As soon as practicable after receiving an application for the modification of a development consent, a consent authority must cause a copy of the application to be given to each concurrence authority and approval body for the development to which the application relates.
(2)  If an application to which this clause applies is made about a development consent granted by a regional panel, the council or councils of the area in which the development concerned is to be carried out are to comply with subclause (1) instead of the regional panel.