99   Public inquiries
(1)  This clause applies to any development application that relates to development with respect to which a public inquiry is directed to be held under Division 2 of Part 6 of the Act.
(2)  The consent authority for the development concerned must cause to be given to each concurrence authority and approval body for that development:
(a)  as soon as practicable after the direction is given, notice of the fact that a public inquiry is to be held, and
(b)  as soon as practicable after the findings and recommendations of the inquiry have been made public, copies of those findings and recommendations and (in the case of development other than designated development) any comments made by the Minister on them.
(3)  At any time within 14 days after receiving a copy of the findings and recommendations arising from the public inquiry:
(a)  a concurrence authority may vary any conditions that it may previously have imposed in relation to its concurrence to the development, and
(b)  an approval body may vary any general terms of approval that it may previously have given in relation to the development.