146   Compliance with conditions of development consent
(cf clause 79H of EP&A Regulation 1994)
A certifying authority must not issue a construction certificate for building work or subdivision work under a development consent unless it is satisfied that each of the following have been complied with:
(a)  each condition or agreement requiring the provision of security before work is carried out in accordance with the consent (as referred to in section 80A (6) of the Act),
(b)  each condition requiring the payment of a monetary contribution before work is carried out in accordance with the consent (as referred to in section 94 or 94A of the Act),