109ZK   Limitation on time when building action or subdivision action may be brought
(1)  Despite any Act or law to the contrary:
(a)  a building action may not be brought in relation to any building work more than 10 years after the date on which the relevant final occupation certificate is issued, and
(b)  a subdivision action may not be brought in relation to any subdivision work more than 10 years after:
(i)  in the case of work completed before the relevant subdivision certificate is issued, the date on which the relevant subdivision certificate is issued, or
(ii)  in the case of work completed after the relevant subdivision certificate is issued, the date on which the compliance certificate that certifies that the work has been completed is issued.
(2)  This section does not operate to extend any period of limitation under the Limitation Act 1969.