Division 3 Duties of a person conducting a business or undertaking
231   Duty of persons conducting businesses or undertakings that manufacture plant
A manufacturer must not supply plant specified in Part 1 of Schedule 5 unless the design of that plant is registered under Part 5.3.
Maximum penalty—
(a)  in the case of an individual—$6,000, or
(b)  in the case of a body corporate—$30,000.
232   Duty of persons conducting businesses or undertakings that import plant
An importer must not supply plant specified in Part 1 of Schedule 5 unless the design of that plant is registered under Part 5.3.
Maximum penalty—
(a)  in the case of an individual—$6,000, or
(b)  in the case of a body corporate—$30,000.
233   Duty of persons conducting businesses or undertakings that supply plant
A supplier must not supply plant specified in Part 1 of Schedule 5 unless the design of that plant is registered under Part 5.3.
Maximum penalty—
(a)  in the case of an individual—$6,000, or
(b)  in the case of a body corporate—$30,000.
234   Duty of persons conducting businesses or undertakings that commission plant
(1)  This clause applies to a person who conducts a business or undertaking that commissions plant.
(2)  The person must not commission an item of plant that is specified in Part 2 of Schedule 5 for use in a workplace unless that item of plant is registered under Part 5.3.
Maximum penalty—
(a)  in the case of an individual—$6,000, or
(b)  in the case of a body corporate—$30,000.
(3)  Nothing in subclause (2) prevents a person from performing any necessary adjustments, tests or inspections as part of the commissioning process before the plant is commissioned at a workplace.