Environmental Planning and Assessment Regulation 2000
Current version for 13 September 2019 to date (accessed 19 November 2019 at 07:16)
Part 9 Division 7B Clause 186O
186O   Installation of fire sprinkler systems in facilities with 1 March 2016 as nominated completion date
(1)  If an approved provider of a facility nominated 1 March 2016 as the nominated completion date for the facility, the approved provider must—
(a)  before 1 September 2013, provide an implementation plan to the Implementation Committee, and
(b)  before 1 March 2014 (and every 1 September and 1 March after that date unless the fire sprinkler system has been installed), provide a progress report to the Implementation Committee.
(2)  An implementation plan is to—
(a)  specify details of the proposed installation of the fire sprinkler system (including any approvals required for the installation), and
(b)  describe any work completed for the purposes of the installation, and
(c)  provide an estimate of the date by which the installation will be completed, and
(d)  specify the capital investment value of installing the fire sprinkler system, and
(e)  be in a form approved by the Implementation Committee, and
(f)  include any other information that the Implementation Committee directs (in its approved form) is to be included in the plan.
(3)  A progress report is to—
(a)  specify any changes to information provided to the Implementation Committee in the implementation plan or an earlier progress report, and
(b)  be in a form approved by the Implementation Committee.
(4)  In this clause, approval means an approval under the Act and includes a development consent, a complying development certificate or any other certificate under Part 6 of the Act.