Environmental Planning and Assessment Regulation 2000
Current version for 15 May 2020 to date (accessed 26 May 2020 at 10:23)
Part 8 Division 2 Clause 146A
146A   Restriction on issue of construction certificates without compliance with planning agreement
If a planning agreement specifies requirements of the agreement that are required to be complied with before a construction certificate for building work is issued, a certifier must not issue a construction certificate for the work unless the certifier is satisfied that those requirements have been complied with.