136E   Development involving bonded asbestos material and friable asbestos material
(1)  A complying development certificate for development that involves building work or demolition work must be issued subject to the following conditions—
(a)  work involving bonded asbestos removal work (of an area of more than 10 square metres) or friable asbestos removal work must be undertaken by a person who carries on a business of such removal work in accordance with a licence under clause 458 of the Work Health and Safety Regulation 2011,
(b)  the person having the benefit of the complying development certificate must provide the principal certifying authority with a copy of a signed contract with such a person before any development pursuant to the complying development certificate commences,
(c)  any such contract must indicate whether any bonded asbestos material or friable asbestos material will be removed, and if so, must specify the landfill site (that may lawfully receive asbestos) to which the bonded asbestos material or friable asbestos material is to be delivered,
(d)  if the contract indicates that bonded asbestos material or friable asbestos material will be removed to a specified landfill site, the person having the benefit of the complying development certificate must give the principal certifying authority a copy of a receipt from the operator of the landfill site stating that all the asbestos material referred to in the contract has been received by the operator.
(2)  This clause applies only to a complying development certificate issued after the commencement of this clause.
(3)  In this clause, bonded asbestos material, bonded asbestos removal work, friable asbestos material and friable asbestos removal work have the same meanings as in clause 317 of the Occupational Health and Safety Regulation 2001.
Note 1.
 Under clause 317 removal work refers to work in which the bonded asbestos material or friable asbestos material is removed, repaired or disturbed.
Note 2.
 The effect of subclause (1) (a) is that the development will be a workplace to which the Occupational Health and Safety Regulation 2001 applies while removal work involving bonded asbestos material or friable asbestos material is being undertaken.
Note 3.
 Information on the removal and disposal of asbestos to landfill sites licensed to accept this waste is available from the Office of Environment and Heritage.
Note 4.
 Demolition undertaken in relation to complying development under the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008 must be carried out in accordance with Australian Standard AS 2601—2001, Demolition of structures.