96   Imposition of conditions—ancillary aspects of development
(cf clause 67A of EP&A Regulation 1994)
(1)  If a consent authority grants development consent subject to a condition authorised by section 80A (2) of the Act with respect to an ancillary aspect of the development, the consent authority may specify the period within which the ancillary aspect must be carried out to the satisfaction of the consent authority, or a person specified by the consent authority, as referred to in that subsection.
(2)  The applicant may produce evidence to the consent authority, or to the person specified by the consent authority for the purpose, sufficient to enable it, or the person so specified, to be satisfied in respect of the ancillary aspect of the development.
(3)  For the purposes of section 80A (3) of the Act, the relevant period is the period of 28 days after the applicant’s evidence is produced to the consent authority or a person specified by the consent authority.