Environmental Planning and Assessment Regulation 2000
Current version for 13 September 2019 to date (accessed 19 November 2019 at 12:09)
Part 6 Division 11 Clause 113B
113B   Period after which Crown development applications may be referred to Minister or regional panel
(1)  For the purposes of section 4.33 (2) of the Act, the prescribed period is 70 days after the Crown development application is lodged with the consent authority.
(2)  For the purposes of section 4.33 (5) of the Act, the prescribed period is 50 days after the Crown development application is referred to the applicable regional panel under section 4.33 (2) (b) of the Act.