113B   Period after which Crown development applications may be referred to Minister or regional panel
(1)  For the purposes of section 4.33 (2) of the Act, the prescribed period is 70 days after the Crown development application is lodged with the consent authority.
(2)  For the purposes of section 4.33 (5) of the Act, the prescribed period is 50 days after the Crown development application is referred to the applicable regional panel under section 89 (2) (b) of the Act.