You are using a version of the website built for webcrawlers and people whose devices cannot use javascript.
Some functionality will not be available.
Contents (2000 - 557)
Skip to content
Environmental Planning and Assessment Regulation 2000
Current version for 1 December 2019 to date (accessed 16 December 2019 at 10:55)
Part 6 Division 11 Clause 107
107   First 2 days after development application is lodged
Neither the day on which a development application is lodged with the consent authority nor the following day are to be taken into consideration in calculating the number of days in any of the assessment periods.