Division 6 Miscellaneous
25   Additional information requested by relevant planning authority
(1)  If an environmental planning instrument requires or permits a development control plan to be prepared and submitted to the relevant planning authority, the planning authority may request the owners (as referred to in section 74D of the Act) who are submitting the plan to provide the planning authority with such additional information as the planning authority considers necessary for the purposes of making the plan.
(2)  Any such request is to be in writing.
(3)  The information that the relevant planning authority may request is limited to information relating to any relevant matter referred to in an environmental planning instrument.
(4)  In accordance with section 74D (6) of the Act, the 60-day period referred to in section 74D (5) of the Act may be extended by the number of days from the day on which the request for the information was made until the day on which the information is provided or on which the owners refuse to supply the information (whichever is the sooner).
(5)  If the owners refuse to supply the requested information, the development control plan is taken not to have been submitted to the relevant planning authority.
25AA   Assessment and preparation fees
(1)  If a draft development control plan under section 74D of the Act is prepared (and submitted to the relevant planning authority) by the owners of the land to which it applies, the owners must pay the relevant planning authority an assessment fee as determined by the planning authority.
(2)  If any such draft development control plan is prepared by the relevant planning authority at the request of the owners (or the percentage of the owners as referred in section 74D (3) of the Act), those owners must pay the planning authority a preparation fee as determined by the planning authority.
(3)  Any such assessment or preparation fee must not exceed the reasonable cost, to the relevant planning authority, of assessing or preparing the draft development control plan, carrying out any associated studies and publicly exhibiting the draft plan.
(4)  If there is more than one owner of the land to which the draft development control plan applies, the fee concerned is to be apportioned between them as the relevant planning authority determines.
(5)  If the Minister, in accordance with section 74D (5) (b) of the Act, acts in the place of a council to make the development control plan concerned, the council must, if directed by the Minister to do so, forward to the Minister any assessment or preparation fee that has been paid to the council in relation to that plan.
(6)  Any assessment or preparation fees payable under clause 272, 273, 273A, 274A or 274B (as in force before their repeal by the Environmental Planning and Assessment Amendment (Planning Instruments and Development Consents) Regulation 2005) are taken to be fees (as determined by the relevant planning authority concerned) payable under this clause. If, under any such repealed clause, a lessee was liable to pay a fee, a reference in this clause to the owner of the land extends to any such lessee.
25AB   Councils to provide copies of development control plans to Secretary
A council must, within 28 days of making a development control plan, provide the Secretary with a copy of the plan.
25AC   Purchase of copies of development control plans
Copies of a development control plan (including any document referred to in a development control plan such as a supporting map, plan, diagram, illustration or other material) are to be made available for purchase from the principal office of the relevant planning authority that prepared the plan.
Note.
 Under section 74E (4) of the Act, a development control plan must be available for inspection (without charge) at the principal office of the relevant planning authority that prepared the plan.
The above clause does not require the relevant planning authority to supply certified copies of any document. Certified copies are supplied under section 150 of the Act on payment of a prescribed fee. The fee for a certified copy is prescribed by clause 262.
25AD   Further transitional provisions: 2005 Amending Act
(1)  In this clause:
deemed DCP means a master plan, in force under a provision of an environmental planning instrument immediately before the relevant commencement, that is taken to be a development control plan under section 74D of the Act because of clause 95 of Schedule 6 to the Act, and includes a master plan that is taken to be a development control plan as provided by subclause (4).
relevant commencement means the date on which Schedule 2 to the 2005 Amending Act commences.
(2) Effect of section 74C on deemed DCPs Section 74C (2) and (5) of the Act (as inserted by the 2005 Amending Act) does not render invalid any deemed DCP until such time as the principal local environmental planning instrument applying to the land concerned adopts the applicable mandatory provisions of the Standard Instrument.
(3) Amendment of deemed DCPs A deemed DCP may be amended or revoked only in accordance with the procedures provided in relation to the making of the master plan by the environmental planning instrument under which it was made. Accordingly, section 74C (4) of the Act does not apply in relation to a deemed DCP.
(4) Pending master plans Any master plan lodged under a provision of an environmental planning instrument but not made or adopted as at the relevant commencement may, after that commencement, proceed to be made or adopted as if the amendments made to the Act and this Regulation by Schedules 2 and 7.3 to the 2005 Amending Act had not been made. Once it is made or adopted, the master plan is taken to be a development control plan under section 74D of the Act.