You are using a version of the website built for webcrawlers and people whose devices cannot use javascript. Some functionality may not be available.
Contents (2000 - 557)
Skip contents
Environmental Planning and Assessment Regulation 2000
Current version for 1 September 2017 to date (accessed 21 September 2017 at 00:43)
Part 1A Clause 8OA
8OA   Transitional provision—projects or concept plans otherwise prohibited for which approval may be given
Clauses 8N and 8O do not apply to a project application if, before the commencement of those clauses, the Secretary had notified the proponent of environmental assessment requirements under section 75F of the Act relating to the project, or part of the project, concerned.