Environmental Planning and Assessment Regulation 2000
Current version for 15 May 2020 to date (accessed 7 June 2020 at 17:17)
Part 17 Clause 281A
281A   Notice of orders under Schedule 5 to the Act
(1)  If a consent authority (other than a council) proposes to give an order under Division 2A of Part 6 of the Act in relation to building work or subdivision work for which the consent authority is not the principal certifier, the consent authority must give the principal certifier notice of its intention to give the order.
(2)  A notice required to be given under subclause (1) by a consent authority or under clause 9(2) of Schedule 5 to the Act by a council must be given within 7 days after the notice of intention to give the order concerned is given under section 121H(1) of the Act.