281A   Notice of orders under Schedule 5 to the Act
(1)  If a consent authority (other than a council) proposes to give an order under Division 2A of Part 6 of the Act in relation to building work or subdivision work for which the consent authority is not the principal certifying authority, the consent authority must give the principal certifying authority notice of its intention to give the order.
(2)  A notice required to be given under subclause (1) by a consent authority or under clause 9 (2) of Schedule 5 to the Act by a council must be given within 7 days after the notice of intention to give the order concerned is given under section 121H (1) of the Act.