268Y   Interpretation
(1)  In this Part—
consent ballot—see clause 268ZC.
co-owner of a lot means a person who owns a lot jointly with 1 or more other persons.
(2)  Words and expressions used in this Part have the same meaning as they have in Schedule 7 to the Act.
268YA   Subdivision works
(1)  For the purposes of the definition of subdivision works in Schedule 7 to the Act, works for the following purposes are prescribed—
(a)  gas supply,
(b)  remediation of contaminated land,
(c)  demolition of a building or work if the demolition is required to carry out other subdivision works.
(2)  In this clause—
contaminated land has the same meaning as in Part 7A of the Act.