244J   Definitions
In this Division—
activity for the purposes of a transacted electricity transmission or distribution network includes activities (within the meaning of Part 5 of the Act) for any one or more of the following purposes—
(a)  development for the purposes of the construction, maintenance or operation of a transacted electricity transmission or distribution network,
(b)  geotechnical investigations relating to a transacted electricity transmission or distribution network,
(c)  environmental management and pollution control relating to a transacted electricity transmission or distribution network,
(d)  access for the purpose of the construction, maintenance or operation of a transacted electricity transmission or distribution network,
(e)  temporary construction sites and storage areas, including temporary batching plants, the storage of plant and equipment and the stockpiling of excavated material.
approved Code means a Code approved by the Minister under this Division.
authorised network operator means an authorised network operator under the Electricity Network Assets (Authorised Transactions) Act 2015.
electricity transmission or distribution network has the same meaning as it has in Division 5 of Part 3 of State Environmental Planning Policy (Infrastructure) 2007.
transacted electricity transmission or distribution network means a transacted distribution system or transacted transmission system under the Electricity Network Assets (Authorised Transactions) Act 2015.