154B   Fulfilment of BASIX commitments
(1)  This clause applies to BASIX affected development in respect of which, and BASIX optional development in respect of which, a relevant BASIX certificate requires a certifying authority to monitor fulfilment of any of the commitments listed in the certificate.
(2)  A certifying authority must not issue an occupation certificate (whether interim or final) for any building resulting from, or any building that becomes a BASIX affected building because of, BASIX affected development or BASIX optional development to which this clause applies, or for any part of such a building, unless each of the commitments whose fulfilment it is required to monitor in relation to the building or part has been fulfilled.
(3)  For the purpose of satisfying itself as to the fulfilment of any such commitment, a certifying authority may rely on the advice of any properly qualified person.