Environmental Planning and Assessment Regulation 2000
Historical version for 30 September 2015 to 1 October 2015 (accessed 5 July 2020 at 20:07) Current version
Part 15 Division 1A Clause 245H
245H   Additional fee for critical infrastructure projects
(1)  The maximum additional fee payable for a Part 3A application in respect of a critical infrastructure project is $50,000.
(2)  If a project is declared to be a critical infrastructure project after the fee for the Part 3A application is paid or due for payment, the additional fee is payable within 14 days after the Secretary notifies the proponent that the additional fee is payable.