105   Notice under section 91A (6) or section 92 (7) of the Act to approval bodies of determination of development application for integrated development
(cf clause 70A of EP&A Regulation 1994)
(1)  A notice under section 91A (6) or section 92 (7) of the Act to an approval body must be sent to the approval body within 14 days after the date of the determination of the relevant development application.
(2)  Failure to send the notice within the 14-day period does not affect the validity of the notice or the development consent (if any) to which it relates.