124D   Review procedures
(1)  The consent authority must give the operator of a development subject to a review condition not less than 14 days written notice that a review is to be carried out under the condition.
(2)  The consent authority may notify such other persons as it thinks fit of the review.
(3)  The consent authority must take into account any submissions made by a person that are received within 14 days after notice is given to the person of a review.
Note.
 Under section 80A (10D) of the Act, a decision to change a review condition of a development consent is taken to be a determination of a development consent and is subject to the notification and appeal provisions under the Act in relation to such a determination.