245N   Meaning of “estimated cost” for determining fee under this Division
(1)  In determining the fee in relation to a project involving the erection of a building, the Director-General must make his or her determination by reference to a genuine estimate of the capital investment value of the project.
(2)  In determining the fee in relation to a project involving the carrying out of a work, the Director-General must make his or her determination by reference to a genuine estimate of the construction costs of the work.
(3)  In determining the fee in relation to a project involving the demolition of a building or work, the Director-General must make his or her determination by reference to a genuine estimate of the costs of demolition.
(4)  In determining the fee in relation to a concept plan for a project, the Director-General may make any necessary assumptions about the detail of the future project that is the subject of the concept plan.
(5)    (Repealed)