225   Savings provisions
(1)  Any building product or system (however described) in respect of which a certificate of conformity under the ABCB scheme was issued before the commencement is taken to have been accredited in accordance with clause 224 as in force after the commencement, subject to the same limitations as to time as those to which the certificate of conformity is subject.
(2)  Any building product or system (however described):
(a)  that was the subject of an application for a certificate of conformity that was lodged under the ABCB scheme before the commencement but had not been determined at the commencement, and
(b)  in respect of which such a certificate of conformity is issued in accordance with that scheme after the commencement,
is taken to have been accredited in accordance with clause 224 as in force after the commencement, subject to the same limitations as to time as those to which the certificate of conformity is subject.
(3)  In this clause:
ABCB scheme has the same meaning as in clause 224 as in force before the commencement.