Environmental Planning and Assessment Regulation 2000
Historical version for 7 September 2009 to 25 October 2009 (accessed 6 June 2020 at 03:22) Current version
Part 16A Clause 268A
268A   Construction certificates, principal certifying authorities, principal contractors and notifications
(1)  Except as otherwise provided by this clause, sections 81A (2), 86 (1) and 109H (3) (b) and (5) (b) of the Act do not apply to the erection of a temporary structure in accordance with a development consent that is granted on or after 26 October 2007 and before 26 October 2009.
(2)  Sections 81A (2) (b) (i), (b1) (i) and (c) and 86 (1) (a) (i), (a1) (i) and (b) of the Act apply in relation to the erection of a tent or marquee that has a floor area greater than 100 square metres and is proposed to be used as a place of public entertainment.