Environmental Planning and Assessment Regulation 2000
Historical version for 1 January 2008 to 31 January 2008 (accessed 15 August 2020 at 13:05) Current version
Part 6 Division 11 Clause 107
107   First 2 days after development application is lodged
Neither the day on which a development application is lodged with the consent authority nor the following day are to be taken into consideration in calculating the number of days in any of the assessment periods.