Environmental Planning and Assessment Regulation 2000
Historical version for 8 July 2005 to 31 July 2005 (accessed 5 August 2020 at 00:48) Current version
Part 6 Division 1 Clause 51
51   Rejection of development applications
(cf clause 47 (1)–(3) of EP&A Regulation 1994)
(1)  A consent authority may reject a development application within 7 days after receiving it if:
(a)  the application is illegible or unclear as to the development consent sought, or
(b)  the application does not contain any information, or is not accompanied by any document, specified in Part 1 of Schedule 1.
(2)  A consent authority may reject a development application within 14 days after receiving it if:
(a1)  being an application for development requiring concurrence, the application fails to include the concurrence fees appropriate for each concurrence relevant to the development, or
(a)  being an application for integrated development, the application fails:
(i)  to identify all of the approvals referred to in section 91 of the Act that are required to be obtained before the development may be carried out, or
(ii)  to include the approval fees appropriate for each approval relevant to the development, or
(iii)  to include the additional information required by this Regulation in relation to the development, or
(b)  being an application referred to in section 78A (8) (b) of the Act, the application is not accompanied by a species impact statement referred to in that paragraph.
(3)  An application that is rejected under this clause is taken for the purposes of the Act never to have been made.
(4)  The consent authority must refund to the applicant the whole of any application fee paid in connection with an application that is rejected under this clause.
(5)  Immediately after the rejection of a development application for:
(a)  development for which the concurrence of a concurrence authority is required, or
(b)  integrated development,
the consent authority must notify each relevant concurrence authority or approval body of the rejection.