58   Relevant planning authority may vary proposals or not proceed
(1)  The relevant planning authority may, at any time, vary its proposals as a consequence of its consideration of any submission or report during community consultation or for any other reason.
(2)  If it does so, the relevant planning authority is to forward a revised planning proposal to the Minister.
(3)  Further community consultation under section 57 is not required unless the Minister so directs in a revised determination under section 56.
(4)  The relevant planning authority may also, at any time, request the Minister to determine that the matter not proceed.