Part 6 Clause 6.2
6.2   Public utility infrastructure
(1)  Development consent must not be granted for development on land in an urban release area unless the Council is satisfied that any public utility infrastructure that is essential for the proposed development is available or that adequate arrangements have been made to make that infrastructure available when it is required.
(2)  This clause does not apply to development for the purpose of providing, extending, augmenting, maintaining or repairing any public utility infrastructure.