18   Temporary development of land
(1)  Despite any other provision of this plan, a person may carry out development on any land with development consent for any purpose for a maximum period of 28 days in any one year.
(2)  Consent may be granted under this clause only if, in the opinion of consent authority, the development contributes to the social, environmental, cultural and economic well-being of the community.
(3)  To avoid doubt, State Environmental Planning Policy No 1—Development Standards does not apply to a requirement made by subclause (1).