Contents (2008 - 380)
Electricity Supply (Safety and Network Management) Regulation 2008
Status information

Part 1 Preliminary

1 Name of Regulation
2 Commencement
3 Definitions
4 Application

Part 2 Disconnection from distribution system

5 Refusal to connect and disconnection of unsafe electrical installations
6 Disconnection where immediate danger
7 Persons on life support systems

Part 3 Plan to be lodged and implemented by network operator

8 Network operators may be required to lodge plan
9 Chapter 1 of plan—network safety and reliability
10 Chapter 2 of plan—customer installation safety
11 Chapter 3 of plan—public electrical safety awareness
12 Chapter 4 of plan—bush fire risk management
13 Director-General may direct network operators to take into account codes, standards or guidelines
14 Network operators to review plans

Part 4 Audit requirements

15 Plan to be audited
16 Nomination of auditor to conduct audit
17 Requirements of audit
18 Additional report requirements—network safety and reliability
19 Additional audits may be required

Part 5 Compliance with plan

20 Availability of plan
21 Network operators to measure and report on network performance
22 Further reports to be submitted to Director-General
23 Certain work to be carried out in accordance with plan
24 Director-General may direct compliance with plan
25 Director-General may direct amendment of plans

Part 6 Miscellaneous

26 Exemptions
27 Savings and transitional

 Schedule 1 Chapter 1 of network management plan—network safety and reliability

Historical notes