85A   Responding to submissions

(1)  The Director-General is to provide to an applicant for State significant development the submissions, or a summary of the submissions, received in relation to the application during the submission period.
(2)  The Director-General may, by notice in writing, require the applicant to provide a written response to such issues raised in those submissions as the Director-General considers necessary.