Local Government (General) Regulation 2005
Current version for 1 March 2013 to date (accessed 25 May 2013 at 16:00)

47   Temporary exemption for purchaser of land

(1)  Despite the other provisions of this Regulation, a person who purchases (or otherwise acquires) land on which any sewage management facilities are installed or constructed may operate a system of sewage management without the approval required under section 68 of the Act for the period of 3 months after the date on which the land is transferred or otherwise conveyed to the person (whether or not an approval is in force, as at that date, in relation to the operation of a system of sewage management on that land).
(2)  Further, if the person duly applies, within the period of 2 months after the date on which the land is transferred or otherwise conveyed to the person, for approval to operate the system of sewage management concerned, the person may continue to operate that system of sewage management without approval until the application is finally determined.
Top of page