Local Government (Manufactured Home Estates, Caravan Parks, Camping Grounds and Moveable Dwellings) Regulation 2005
Current version for 1 July 2012 to date (accessed 22 May 2013 at 15:51)
Subdivision 3 Construction
150 Termite shields
Shields, barriers or the like must be provided in accordance with
AS 3660.1–2000
Termite management—new building work (as in force
on 1 September 2005) to protect any structural members that are susceptible to
attack by termites.
151 Glazing
Glazing materials must be selected and installed in accordance
with the relevant provisions of AS
1288—1994, Glass in buildings—Selection and
installation and, to the extent to which those provisions
require the use of safety glass, in accordance with the relevant provisions of
AS/NZS 2208:1996, Safety
glazing materials in buildings (each as in force on 1
September 2005).
152 External waterproofing
The roof, external walls, door frames and window frames of a
relocatable home must be constructed so as to prevent rain or dampness
penetrating to the inner parts of the home.
153 Internal waterproofing
(1) The floor of a bathroom, shower room or room containing a toilet
or washing machine in a relocatable home must consist of, or be covered by,
material that is impervious to water.
(2) The wall surface of a shower enclosure (or, in the case of a
shower that is not enclosed, any wall surface within 1.5 metres of the shower
fitting) must be impervious to water to a height of at least 1.8 metres above
the floor.
(3) Any wall surface within 75 millimetres of a bath, basin or other
similar bathroom appliance must be impervious to water to a height of at least
150 millimetres above the appliance.
(4) Compliance with AS
3740—2004, Waterproofing of wet areas within
residential buildings (as in force on 1 September 2005)
satisfies the requirements of this clause.
154 Plumbing and drainage
(1) All pipes and fittings in a relocatable home that relate to water
supply or sewerage must be installed in accordance with:(a) the Plumbing and Drainage Act
2011 and any regulations under that Act,
and
(b) the requirements of any relevant statutory
body.
(2) All pipes and fittings in a relocatable home that relate to
stormwater drainage must be installed in accordance with:(a) the Plumbing Code of Australia, and
(b) the requirements of any relevant statutory
body.
155 Electrical wiring
The electrical wiring in a relocatable home must comply with the
requirements of AS/NZS 3000:
2000, Electrical installations (known as the
Australian/New Zealand Wiring Rules) (as in force on 1 September
2005).
156 Fire and smoke alarms
(1) A relocatable home must be equipped with an automatic fire
detection and alarm system that complies with the requirements of Part 3.7.2
of Volume Two of the Building Code of
Australia in relation to class 1 (a) buildings within the
meaning of that Code.
(2) This clause does not apply to a relocatable home that was
constructed before 1 January 1996, whether installed before, on or after that
date.
(3) (Repealed)