103   Energy savings scheme targets

(1)  The energy savings scheme targets are to be used as the basis for the calculation of each scheme participant’s individual energy savings target.
(2)  The energy savings scheme targets are set out in Schedule 5.
(3)  The energy savings scheme target for a year specified in column 1 of Schedule 5 is the amount specified for that year in column 2 of that Schedule.
Note. The energy savings scheme target is applied to the liable acquisitions made by a scheme participant to calculate an individual energy savings target for the scheme participant. This is explained in Division 4.