309 Connections
(1) On a water supply authority’s water main or a sewer main
becoming available for connection, the water supply authority may:(a) publish in the Gazette notice of its availability,
and
(b) give such other notices as may be
prescribed.
(2) A landholder of land to which a notice under subsection (1) (a)
relates becomes liable:(a) in the case of a water main, to payment of water service charges
after the expiration of 21 days from publication of the notice,
or
(b) in the case of a sewer main, to payment of sewerage service
charges after the expiration of 21 days from publication of the
notice.
(3) If a landholder does not make a connection to the water supply
authority’s water main or sewer main before becoming liable under
subsection (2), the water supply authority may make the connection at the
expense of the landholder.
(4) Any amount due to a water supply authority for a connection made
under subsection (3) is a charge on the land connected and may be recovered as
a debt owed to the water supply authority by the landholder of the
land.
(5) If a landholder of land fails:(a) to connect the land to a water supply authority’s water main
or sewer main before becoming liable under subsection (2),
or
(b) to do any work that by this Part is required to be done by the
landholder,
the occupier of the land may make the connection or do the work and, in
accordance with subsection (6), recover the cost from the
landholder.
(6) An amount (including interest) recoverable under subsection (5) by
an occupier from a landholder may be recovered:(a) by deducting it from any rent from time to time payable to the
landholder by the occupier, or
(b) as a debt owed to the occupier by the
landholder.
(7) Any person desiring to connect premises with a water supply
authority’s water main or sewer main may (subject to such conditions as
may be imposed by law) open up the surface and soil of any road or way, public
or private, or any footpath or public reserve to the extent required to make
the connection.