Water Management Act 2000 No 92
Historical version for 15 July 2001 to 16 July 2001 (accessed 25 May 2013 at 18:59) Current version
Chapter 6Part 1Section 282

282   Review of activities of major utilities

(1)  The activities of a major utility under this Act:
(a)  may be reviewed at any time, and
(b)  must be reviewed:
(i)  before the end of the 6 month period following the date on which its first approval was granted under section 95, and
(ii)  before the end of each 5 year period following the date on which its current approval was granted.
(2)  For the purpose of conducting such a review, the Minister must cause notice to be published:
(a)  in the Gazette, and
(b)  in a newspaper circulating throughout New South Wales,
      inviting written submissions from interested persons in relation to the activities of the major utility during the period under review.