122C   Minister may require monitoring or environmental audits by imposition of conditions on approved project

(1)  The Minister may, by the imposition of conditions on the approval for a project, require monitoring or an environmental audit or audits to be undertaken to the satisfaction of the Minister by the proponent of the project.
(2)  A condition requiring monitoring or an environmental audit may be imposed at the time the approval for the project is given or at any other time by notice in writing to the proponent of the project.
(3)  Any such condition imposed by notice may be varied or revoked by a similar notice.