Environmental Planning and Assessment Act 1979 No 203
Current version for 19 November 2014 to date (accessed 22 December 2014 at 06:25)
Part 4Division 9Section 101

101   Validity of development consents and complying development certificates

If public notice of the granting of a consent or a complying development certificate is given in accordance with the regulations by a consent authority or an accredited certifier, the validity of the consent or certificate cannot be questioned in any legal proceedings except those commenced in the Court by any person at any time before the expiration of 3 months from the date on which public notice was so given.